Municipal Buildings Retrofit, repairs and upgrades
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022202320242025
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Gauthier
- Construction start
- Jul 12, 2021(actual)
- Construction end
- Jul 25, 2025(actual)
Against the original forecast
- Construction end19 months lateforecast Dec 29, 2023
Also in Gauthier
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60134 in the federal list. How to read these figures.