Revitalization of Lynch Lake Park

Joly, Ontario

completeActive TransportationCVRIS
Federal contribution
$74,000
Federal share84%

of $88.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022202320242025
Built

Approved 3 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Joly
Construction start
Sep 13, 2023(actual)
Construction end
Dec 23, 2024(actual)

Against the original forecast

  • Construction end3 months lateforecast Sep 30, 2024