Rehabilitation of Lions Trail in Newcastle
Federal contribution
$115,863
Federal share80%
of $144.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
20222023
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the Municipality of Clarington
- Construction start
- Jul 25, 2022(actual)
- Construction end
- Aug 23, 2023(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Sep 29, 2023
Also in Clarington
- Concession Road 6 Pavement Rehabilitation - Old Scugog Road to Acres Road$826.7K
- Road Rehabilitation - Regional Highway 2$375.0K
- Renovation of Shaw House$240.0K
- Bowmanville Avenue (RR57) - Multi-Use Path - Baseline Road to Hwy 2 - Bowmanville, Clarington, Ontario$232.6K
- Baseline Road Bridge Reconstruction$227.1K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60174 in the federal list. How to read these figures.