MacLennan Hall Active Transportation Hub
Federal contribution
$79,984
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- The Township of Tarbutt
- Construction start
- Sep 28, 2021(actual)
- Construction end
- Oct 31, 2022(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60176 in the federal list. How to read these figures.