Back to projects

Install 2 - Generac Generators for back up power

Leeds and Grenville, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$120,420
Federal share80%

of $150.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 19, 2021(actual)
Construction end
Dec 9, 2023(actual)

Against the original forecast

  • Construction end14 months lateforecast Oct 1, 2022

Also in Leeds and Grenville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60187 in the federal list. How to read these figures.