Install 2 - Generac Generators for back up power
Federal contribution
$120,420
Federal share80%
of $150.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- United Counties of Leeds and Grenville
- Construction start
- Jul 19, 2021(actual)
- Construction end
- Dec 9, 2023(actual)
Against the original forecast
- Construction end14 months lateforecast Oct 1, 2022