East Sanitary Trunk Sewer and EDC Rehabilitation

Mississauga, Ontario

completeDisaster MitigationCVRIS
Federal contribution
$6.4M
$6,400,000
Federal share80%

of $8.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
2022202320242025
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 17, 2022(actual)
Construction end
Dec 13, 2024(actual)

Against the original forecast

  • Construction end16 months earlyforecast Mar 31, 2026