Behchoko - New Subdivision Roads in Rae
Behchokö (Rae-Edzo), Northwest Territories
Federal contribution
$3.7M
$3,656,250
Federal share75%
of $4.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 23, 2021
today
2022202420262028
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Community Government of Behchoko
- Construction start
- Jul 1, 2023(actual)
- Construction end
- Oct 24, 2028(forecast)
Against the original forecast
- Construction start4 weeks earlyforecast Aug 1, 2023
Also in Behchokö (Rae-Edzo)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60247 in the federal list. How to read these figures.