North Slave Regional Community Landfills Waste Diversion and Improvement Program

Behchokö (Rae-Edzo), Northwest Territories

underwaySolid Waste ManagementGIS
Federal contribution
$1.1M
$1,113,750
Federal share75%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2021
today
2022202420262028
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 20, 2023(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start13 months lateforecast Jun 1, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60297 in the federal list. How to read these figures.