Schoolyard repairs and various finishes

Saint-Tite, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$309,759
Federal share53%

of $580.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Nov 5, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end5 weeks earlyforecast Dec 10, 2021

Also in Saint-Tite

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60330 in the federal list. How to read these figures.