Repair of the exterior cladding
Federal contribution
$288,000
Federal share80%
of $360.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 21, 2021(actual)
- Construction end
- May 16, 2022(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2021
- Construction end5 months earlyforecast Sep 30, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60337 in the federal list. How to read these figures.