Paulatuk Sewage Lagoon Upgrade

Paulatuk, Northwest Territories

completeWastewaterGIS
Federal contribution
$348,750
Federal share75%

of $465.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2021
20222023202420252026
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Hamlet of Paulatuk
Construction start
Jul 4, 2023(actual)
Construction end
Oct 31, 2025(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 1, 2023
  • Construction end12 months earlyforecast Oct 31, 2026