Health PEI Flooring Replacement

O'Leary, Prince Edward Island

completeHealthcare InfrastructureCVRIS
Federal contribution
$160,000
Federal share80%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Health PEI
Construction start
Sep 1, 2023(actual)
Construction end
May 10, 2024(actual)