Gitsegukla Indian Band - Gitsegukla Community Kitchen Retrofit
Federal contribution
$398,500
Federal share100%
of $398.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Gitsegukla Band
- Construction start
- Aug 31, 2023(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction start18 months lateforecast Mar 1, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60402 in the federal list. How to read these figures.