Highland Manor - Facility Upgrades

Neil's Harbour, Nova Scotia

completeVentilationCVRIS
Federal contribution
$49,365
Federal share80%

of $61.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
20222023
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Highland Manor
Construction start
May 19, 2021(actual)
Construction end
Jan 27, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2021
  • Construction end4 weeks lateforecast Dec 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60408 in the federal list. How to read these figures.