Musquodoboit Valley Home for Special Care - Facility Upgrades
Middle Musquodoboit, Nova Scotia
Federal contribution
$124,964
Federal share80%
of $156.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Musquodoboit Valley Home for Special Care
- Construction start
- Jan 22, 2022(actual)
- Construction end
- Jun 25, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Dec 1, 2021
- Construction end3 months lateforecast Mar 31, 2022
Also in Middle Musquodoboit