North Queens Nursing Home - Facility Upgrade
Federal contribution
$18,400
Federal share80%
of $23.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- North Queens Nursing Home
- Construction start
- May 25, 2022(actual)
- Construction end
- Jun 16, 2022(actual)
Against the original forecast
- Construction start6 months lateforecast Nov 22, 2021
- Construction end3 months lateforecast Mar 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60417 in the federal list. How to read these figures.