Northwood Bedford Incorporated - Facility Upgrades
Federal contribution
$737,620
Federal share80%
of $922.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Northwood Bedford Incorporated
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Aug 1, 2022(actual)
Against the original forecast
- Construction end4 months lateforecast Mar 31, 2022
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60419 in the federal list. How to read these figures.