Back to projects

Northwood Bedford Incorporated - Facility Upgrades

Bedford, Nova Scotia

completeHealthcare InfrastructureCVRIS
Federal contribution
$737,620
Federal share80%

of $922.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
2022
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 7, 2021(actual)
Construction end
Aug 1, 2022(actual)

Against the original forecast

  • Construction end4 months lateforecast Mar 31, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60419 in the federal list. How to read these figures.