Northwood Halifax Incorporated - Facility Upgrades
Federal contribution
$814,740
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Northwood Halifax Incorporated
- Construction start
- Oct 25, 2021(actual)
- Construction end
- Sep 30, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 22, 2021
- Construction end4 months lateforecast May 31, 2022
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60420 in the federal list. How to read these figures.