Back to projects

Rosedale Home for Special Care - Facility Upgrades

New Germany, Nova Scotia

completeHealthcare InfrastructureCVRIS
Federal contribution
$47,910
Federal share80%

of $59.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 3, 2021(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 15, 2021
  • Construction end3 months earlyforecast Dec 31, 2021

Also in New Germany

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60425 in the federal list. How to read these figures.