Sioux Lookout Student and Family Housing
Federal contribution
$2.2M
$2,190,951
Federal share80%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Kenora District Services Board
- Construction start
- Aug 9, 2021(actual)
- Construction end
- Jan 12, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast May 3, 2021
- Construction end2 months lateforecast Oct 28, 2022
Also in Sioux Lookout
- Pelican Falls High School COVID-19 Retrofit$6.7M
- Sioux Lookout Airport Terminal Building Expansion and Renovation$4.2M
- Ka-Na-Chi-Hih Treatment Centre Sioux Lookout Program Expansion$1.4M
- Development of Cultural Centre for Youth and the Arts$1.3M
- Improvements to the Seventh Avenue Sewer and Road System$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60453 in the federal list. How to read these figures.