Marten Falls First Nation Portable Classroom

Marten Falls First Nation, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$160,100
Federal share80%

of $201.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Marten Falls First Nation
Construction start
Nov 10, 2022(actual)
Construction end
Mar 20, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Oct 1, 2022
  • Construction end7 months earlyforecast Oct 31, 2023