Neskantaga First Nation Portable Classroom

Neskantaga First Nation, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$161,000
Federal share80%

of $201.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Neskantaga First Nation
Construction start
Oct 3, 2022(actual)
Construction end
Aug 18, 2023(actual)

Against the original forecast

  • Construction end16 months earlyforecast Dec 20, 2024

Also in Neskantaga First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60473 in the federal list. How to read these figures.