Nibinamik First Nation Portable Classroom

Nibinamik First Nation, Ontario

completeOtherCVRIS
Federal contribution
$161,000
Federal share80%

of $201.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Nibinamik First Nation
Construction start
May 28, 2021(actual)
Construction end
Jul 30, 2024(actual)

Against the original forecast

  • Construction start16 months earlyforecast Oct 1, 2022
  • Construction end5 months earlyforecast Dec 20, 2024

Also in Nibinamik First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60474 in the federal list. How to read these figures.