Matawa Education and Care Centre (MECC) Gymnasium

Thunder Bay, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$3.0M
$3,044,775
Federal share80%

of $3.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 24, 2022(actual)
Construction end
Oct 5, 2023(actual)