Back to projects

Pauquachin Ardmore Kitchen and Servery Renovation

Pauquachin First Nation, British Columbia

completeOtherCVRIS
Federal contribution
$295,000
Federal share100%

of $295.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
First Nation of Pauquachin
Construction start
Oct 7, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start3 months earlyforecast Dec 30, 2022
  • Construction end15 months earlyforecast Mar 31, 2025