Thompson-Nicola - Blackpool Volunteer Fire Hall Addition
Thompson-Nicola, British Columbia
Federal contribution
$295,629
Federal share80%
of $369.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Regional District of Thompson-Nicola
- Construction start
- Dec 13, 2021(actual)
- Construction end
- Mar 15, 2024(actual)
Against the original forecast
- Construction start3 months earlyforecast Mar 1, 2022
- Construction end13 months earlyforecast Mar 31, 2025