Port Clements - Wastewater System Upgrading
Port Clements, British Columbia
Federal contribution
$1.4M
$1,370,332
Federal share40%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2021
20222023202420252026
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Village of Port Clements
- Construction start
- Jul 16, 2024(actual)
- Construction end
- Mar 31, 2026(forecast)
Against the original forecast
- Construction start3 months lateforecast Apr 30, 2024
Also in Port Clements