Olde Clover Village - Multipurpose Athletic Courts
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Lucan Biddulph
- Construction start
- May 15, 2023(actual)
- Construction end
- Jul 18, 2023(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Jul 3, 2023
- Construction end6 weeks earlyforecast Aug 31, 2023
Also in Lucan Biddulph
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60496 in the federal list. How to read these figures.