Pender Islands Health Care Society - Pender Islands Health Centre HVAC and Generator Replacement
Pender Island, British Columbia
Federal contribution
$131,226
Federal share80%
of $164.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Pender Islands Health Care Society
- Construction start
- Apr 26, 2021(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2021
- Construction end3 months earlyforecast Mar 1, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60500 in the federal list. How to read these figures.