Pender Islands Health Care Society - Pender Islands Health Centre HVAC and Generator Replacement

Pender Island, British Columbia

completeVentilationCVRIS
Federal contribution
$131,226
Federal share80%

of $164.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 26, 2021(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Apr 1, 2021
  • Construction end3 months earlyforecast Mar 1, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60500 in the federal list. How to read these figures.