Cowichan Tribes - Indian Road Active Transportation Path
Cowichan Tribes First Nation, British Columbia
Federal contribution
$813,191
Federal share100%
of $813.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
2022
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cowichan Tribes
- Construction start
- Aug 24, 2021(actual)
- Construction end
- Jun 24, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jul 15, 2021
- Construction end7 months lateforecast Nov 30, 2021
Also in Cowichan Tribes First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60521 in the federal list. How to read these figures.