Galiano Island Recycling Resources Society - Recycling Depot Infrastructure Upgrade to Improve COVID 19 Safety

Galiano Island, British Columbia

completeSolid Waste ManagementCVRIS
Federal contribution
$306,681
Federal share80%

of $383.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 18, 2023(actual)
Construction end
Dec 27, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Mar 31, 2023

Also in Galiano Island

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60522 in the federal list. How to read these figures.