Elkford - Downtown Elkford Active Transportation
Federal contribution
$480,000
Federal share80%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 15, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- District Municipality of Elkford
- Construction start
- Jul 1, 2023(actual)
- Construction end
- Oct 27, 2023(actual)
Against the original forecast
- Construction start4 months lateforecast Mar 1, 2023
- Construction end5 weeks earlyforecast Nov 30, 2023
Also in Elkford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60526 in the federal list. How to read these figures.