Elkford - Downtown Elkford Active Transportation

Elkford, British Columbia

completeActive TransportationCVRIS
Federal contribution
$480,000
Federal share80%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 1, 2023(actual)
Construction end
Oct 27, 2023(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 1, 2023
  • Construction end5 weeks earlyforecast Nov 30, 2023

Also in Elkford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60526 in the federal list. How to read these figures.