Back to projects

Hixon Volunteer Fire Department Society - Hixon Fire Hall Upgrade

Hixon, British Columbia

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$831,926
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 17, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 14, 2022(actual)
Construction end
Dec 19, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast May 6, 2022
  • Construction end6 weeks earlyforecast Jan 31, 2023

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60546 in the federal list. How to read these figures.