Hixon Volunteer Fire Department Society - Hixon Fire Hall Upgrade
Federal contribution
$831,926
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 17, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Hixon Volunteer Fire Department Society
- Construction start
- Jul 14, 2022(actual)
- Construction end
- Dec 19, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast May 6, 2022
- Construction end6 weeks earlyforecast Jan 31, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60546 in the federal list. How to read these figures.