West Vancouver - Baden Powell Trail Section Restoration

West Vancouver, British Columbia

completeActive TransportationCVRIS
Federal contribution
$184,000
Federal share80%

of $230.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 14, 2021(actual)
Construction end
Jun 1, 2022(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2021

Also in West Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60551 in the federal list. How to read these figures.