Back to projects

Lake Country - Bottom Wood Lake Road Improvements (Nexus to Beaver Lake Road)

Lake Country, British Columbia

completeActive TransportationCVRIS
Federal contribution
$529,247
Federal share80%

of $661.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
202220232024
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 30, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 15, 2021

Also in Lake Country

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60557 in the federal list. How to read these figures.