Larch Hills Nordic Society - Trail Lighting

North Okanagan, British Columbia

completeActive TransportationCVRIS
Federal contribution
$144,348
Federal share80%

of $180.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Larch Hills Nordic Society
Construction start
Jun 15, 2022(actual)
Construction end
Oct 19, 2022(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 16, 2022
  • Construction end8 weeks earlyforecast Dec 15, 2022

Also in North Okanagan