West Kelowna - Shannon Lake Active Transportation Corridor: Phase 2B (Segment 7)

West Kelowna, British Columbia

completeActive TransportationCVRIS
Federal contribution
$778,488
Federal share80%

of $973.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
20222023
Built

Approved 7 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
District of West Kelowna
Construction start
Sep 20, 2021(actual)
Construction end
Jul 5, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jul 5, 2021
  • Construction end5 months earlyforecast Dec 5, 2023

Also in West Kelowna

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60567 in the federal list. How to read these figures.