Back to projects

Regional Municipality of Wood Buffalo Kiyam Community Park

Regional Municipality of Wood Buffalo, Alberta

completeActive TransportationCVRIS
Federal contribution
$4.1M
$4,089,600
Federal share80%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 8, 2021(actual)
Construction end
Oct 21, 2024(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Apr 14, 2021
  • Construction end2 months earlyforecast Dec 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60590 in the federal list. How to read these figures.