Back to projects

Halifax Water - Cogswell District Energy System

Halifax, Nova Scotia

underwayGreen EnergyGIS
Federal contribution
$5.6M
$5,598,400
Federal share23%

of $23.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2021
today
20222024202620282030
BuiltForecast
Program
Green Infrastructure Stream
Construction start
May 18, 2023(actual)
Construction end
Jan 31, 2030(forecast)

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60677 in the federal list. How to read these figures.