Vernon River Confederation Trail Structure
Vernon Bridge, Prince Edward Island
Federal contribution
$500,000
Federal share50%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Construction start
- May 30, 2022(actual)
- Construction end
- Nov 4, 2022(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60680 in the federal list. How to read these figures.