Rue Marcoux - Bois-Joli

Bois-Joli, New Brunswick

completeWastewaterCVRIS
Federal contribution
$2.3M
$2,256,935
Federal share80%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
202220232024
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Bois-Joli
Construction start
Jul 1, 2022(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 15, 2022
  • Construction end2 months lateforecast May 31, 2024