Schedule
Announced and approvedAug 3, 2021
202220232024
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Bois-Joli
- Construction start
- Jul 1, 2022(actual)
- Construction end
- Jul 31, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 15, 2022
- Construction end2 months lateforecast May 31, 2024