SaskPower Distributed Generation (DG) Enablement

Cambria No. 6, Saskatchewan

completeGreen EnergyGIS
Federal contribution
$3.5M
$3,462,073
Federal share50%

of $6.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
2022202320242025
Built

Approved 2.9 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
SaskPower
Construction start
Aug 12, 2021(actual)
Construction end
Sep 30, 2025(actual)

Against the original forecast

  • Construction end6 months earlyforecast Mar 31, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60682 in the federal list. How to read these figures.