Halifax Water Commission – Solar Energy for Facilities

Halifax, Nova Scotia

underwayGreen EnergyGIS
Federal contribution
$670,142
Federal share36%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 16, 2021
today
202220232024202520262027
BuiltForecast

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 23, 2022(actual)
Construction end
Dec 31, 2026(forecast)

Against the original forecast

  • Construction start2 months lateforecast Jul 11, 2022

Also in Halifax