Fort Good Hope - Chipseal
Fort Good Hope, Northwest Territories
Federal contribution
$2.7M
$2,658,339
Federal share75%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 23, 2021
today
2022202420262028
BuiltForecast
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Charter Community of K'asho Got'ine
- Construction start
- May 1, 2026(forecast)
- Construction end
- Dec 31, 2028(forecast)
Also in Fort Good Hope
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60733 in the federal list. How to read these figures.