Announced and approvedAug 4, 2021
2022202320242025
Built
Approved 3 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of Mcnab/Braeside
- Construction start
- Jul 18, 2024(actual)
- Construction end
- May 16, 2025(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2024
- Construction end5 months lateforecast Dec 20, 2024