Centennial Park Rehabilitation Phase 2

Englehart, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Englehart
Construction start
Jul 31, 2023(actual)
Construction end
Aug 31, 2023(actual)

Against the original forecast

  • Construction start23 months lateforecast Aug 24, 2021
  • Construction end11 months lateforecast Sep 30, 2022