Back to projects

Station Access and Safety

Burnaby, British Columbia

underwayPublic TransitPTIS
Federal contribution
$25.3M
$25,270,000
Federal share40%

of $63.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
today
2022202420262028
BuiltForecast

Approved 3 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Feb 5, 2023(actual)
Construction end
Dec 24, 2027(forecast)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60986 in the federal list. How to read these figures.