Pump House Electrical Phase II

West St. Modeste, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$51,444
Federal share40%

of $128.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
Town of West St. Modeste
Construction start
Sep 21, 2022(actual)
Construction end
May 13, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2022
  • Construction end5 months lateforecast Dec 15, 2022

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61056 in the federal list. How to read these figures.