Last Mountain Regional Landfill - Cell 4 Closure Plan and Long Term Closure Plan

Bulyea, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$118,560
Federal share40%

of $296.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 15, 2022(actual)
Construction end
Oct 15, 2022(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Nov 30, 2022

Also in Bulyea

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61080 in the federal list. How to read these figures.