Rural Municipality of Excelsior No. 166 - Landfill Decommissioning

RM of Excelsior No. 166, Saskatchewan

completeSolid Waste ManagementGIS
Federal contribution
$267,339
Federal share40%

of $668.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2022
2022202320242025
Built

Approved 8 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Apr 7, 2025(actual)
Construction end
Aug 22, 2025(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Jun 2, 2025
  • Construction end7 months earlyforecast Mar 31, 2026

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61086 in the federal list. How to read these figures.